Check out Joel's article on scheduling. We got:
- 100% completion criteria, just like IMP/IMS and Deliverable Based Planning,
- Measures of Physical Percent Complete, just ANS-748B Earned Value
- Decomposition of the work, just like MIL-STD 881A
- Tracking of effort versus value, just like ANSI-748B BCWP
- Estimating future performance from past performance, just like DID-81650
- Simple descriptions of work, just like Work Package, Planning Packages and Control Account programmatic architecture
- Active project management, just like Program Planning and Controls IMP/IMS processes in every aerospace and defense contractor
- Managing scope, just like every Change Control process found in aerospace and defense